Time limit for disposal by |
|
| S.No |
Subject |
AEE/AE |
DEE |
EE |
SE |
CE |
Remarks |
| I |
A) Preparation of Estimatescosting Less than Rs. 10,00,000/-
|
|
|
|
|
|
|
a) Maintenance/
Repairs |
7
days |
3 days |
5 days |
- |
- |
|
| b) Buildings (Original work) |
15
days |
5 days |
10 days |
- |
- |
|
c) Roads without
CD works i.e. only formation |
15
days |
5 days |
10 days |
- |
- |
|
| d) Roads including Minor C.D. works and M.I. works MPWS Schemes. |
15
days |
5 days |
10 days |
- |
- |
|
| |
|
|
|
|
|
|
|
| |
B) Works costing more than Rs . 10,00,000/- and up to Rs . 50,00,000/-
|
|
|
|
|
|
|
| |
a) Buildings
(original works) |
1
month |
5 days |
7 days |
10 days |
- |
|
| |
b) Roads including Major CD works & PWS Schemes |
1
month |
5 days |
7 days |
10 days |
- |
|
| |
|
|
|
|
|
|
|
| |
C) Works costing more than Rs . 50,00,000/- |
|
|
|
|
|
|
| |
a) Buildings |
11/2
months |
5 days |
7 days |
10 days |
20 days |
|
| |
b) Roads including Major C.D. works & PWS Schemes |
11/2
months |
5 days |
7 days |
10 days |
20 days |
|
| |
|
|
|
|
|
|
|
| II |
Preparation
and processing
of works bills |
5
days |
3 days |
3 days |
- |
- |
Section
officer
should prepare running work bills every fortnight |
| |
|
|
|
|
|
|
|
| III |
Period of
completion
of works |
|
|
|
|
|
|
| |
a) Formation of Roads |
- |
- |
- |
- |
- |
3 months |
| |
b) Roads including Metalling & Minor C.D.works |
- |
- |
- |
- |
- |
9 months |
| |
c) Major C.D.
works & BT Roads. |
- |
- |
- |
- |
- |
12 months |
| |
d) Buildings
costing less
than Rs . 10
lakhs |
- |
- |
- |
- |
- |
6 months |
| |
e) Buildings costing more than Rs . 10 lakhs and up to Rs.50 lakhs |
- |
- |
- |
- |
- |
9 months |
| |
f) Buildings costing more than Rs . 50 lakhs & up to 100 lakhs |
- |
- |
- |
- |
- |
12 months |
| |
g) Buildings
costing more
than Rs . 100
lakhs and up
to 300 lakhs. |
- |
- |
- |
- |
- |
15 months |
| |
h) Buildings
costing more
than Rs . 300
lakhs |
- |
- |
- |
- |
- |
18 months |
| |
|
|
|
|
|
|
|
| IV |
Reports |
|
|
|
|
|
|
| |
Submission
of any data/ information
required for finalisation
of the reports. |
10
days |
3 days |
5 days |
10 days |
|
|
| |
|
|
|
|
|
|
|
| V |
Inspection
Reports |
|
|
|
|
|
|
| |
a) Specific allegations
on works in progress |
- |
- |
- |
- |
- |
|
| |
b) Specific allegations
on completed
works |
- |
- |
- |
- |
- |
To be processed with in 11/2 months |
| |
c) Allegations of general nature. |
- |
- |
- |
- |
- |
To be processed with in 11/2 months |
| |
d) Action on inspection
reports |
- |
- |
- |
- |
- |
Rectifications to be done in one week for works costing less than Rs.10 lakhs & 15 days for works costing more than Rs.10 lakhs and compliance reported by Executive Engineer to Superintending Engineer & Chief Engineer. |