PUBLIC HEALTH  ITEMS
S.No. Description Unit SS Rate for            2003-2004
1 2 3 4
1 RATES OF LABOUR (SKILLED WORKMEN)
1.  Caulkar Per Day  As per common SSR
2.  Plumber 1st Class Per Day
3.  Plumber 2nd Class Per Day
4.  Sewer Cleaner Per Day
5.  Well Sinker Per Day
6.  Pipe line Fitter 1st Class Per Day
7.  Pipe line Fitter 2nd Class Per Day
8.  Pump Driver Per Day
9.  Bore Mechanic Per Day
10. Light Vehicle Driver Per Day
Note:The rate at relevant item in common SSR is applicable for occasional employment.
2 RATES FOR WORK :
a. Earth work excavation in all soils for pipe lines, for drainage and water supply, where the depth is 1.5 times or more than the width. AS PER COMMON SSR 
b. Earth work excavation in all soils for pipe lines, for drainage and water supply, where the depth is less than 1.5 times the width.
c. Earth work excavation in all soils for open trenches, for valve pits, inspection chambers, etc.
3. a. Excavation of pipe line trenches for drainage and water supply in rock requiring blasting with initial lead and lift including cost of blasting materials where the depth is 1.5 times more than the width, in places where there is no habitation.
b. Excavation of pipe line trenches for drainage and water supply in rock requiring blasting with initial lead and lift including cost of blasting materials where the depth is less than 1.5 times the width, in places where there is no habitation.
c. Cutting rock for pipe line trenches by hammers, nuckles and chisels including stacking where the depth is 1.5 times or more than the width.
d. Cutting rock for pipe line trenches by hammers, nuckles and chisels including stacking where the depth is less than 1.5 times the width.
e. Cutting rock for works other than pipe lines trenches by hammers, nuckles and chisels including stacking.
f. For contol blasting at restricted places 25% extra over relevant SSR item
NOTE :-  Rock should be measured in solids. In case it is not possible, stacks should be made in which case 40% for voids to be deducted from the stack measurements.
4 Loading or unloading materials such as C.I. Pipes, PVC Pipes, AC Pressure Pipes, DI Pipes, SW Pipes, PVC Pipes, A.C/Specials less than 300 mm dia upto 4 m in length including stacking.
a. C.I. Pipes/D.I. Pipes and fittings             Per Tonne 48.60
b. A.C. Pipes & Specials                                  Per Tonne 40.50
c. Stoneware pipes & Specials                           Per Tonne 40.70
d. P.V.C. Pipes and fittings                                Per Tonne 40.00
5 Loading or unloading materials such as C.I. Pipes, DI pipes, SW pipes, AC pressure pipes & fittings/ specials from 300 mm to 600 mm dia upto 4 m in length including stacking.
a. C.I. Pipes/D.I. Pipes and fittings             Per Tonne 60.80
b. A.C. Pipes & Specials                                   Per Tonne 55.20
c. Stoneware pipes & Specials                         Per Tonne 55.50
6 Loading or unloading materials such as C.I. Pipes, DI pipes, PVC pipes, AC pipes less than 300 mm dia, above 4 m in length including stacking.
a. C.I. Pipes/D.I. Pipes and fittings              Per Tonne 60.10
b. A.C. Pipes & Specials                                   Per Tonne 55.20
c. P.V.C. Pipes and fittings                                Per Tonne 54.80
Note:- For loading and unloading the above materials at Railway Stations, the rates may be adopted based on the competitive quotations or the hammalae charges if prevailing.
7 Loading or unloading materials such as C.I. Pipes, DI pipes, AC pipes from 300 mm to 600 mm above 4 m in length including stacking excluding 300 mm dia in length above 4 m length, including stacking.
a. C.I. Pipes/D.I. Pipes and fittings              Per Tonne 72.90
b. A.C. Pipes & Specials                                  Per Tonne 68.40
8. a. Lowering the C.I. Pipes, D.I. Pipes and fittings with S/S ends carefully into the trenches and laying them true to alignment and gradient including all sundries, but excluding conveyance from source of supply as per BIS No.3114/85.
DIAMETER OF PIPE : (S/S Pipes) in mm :
80 Per Metre 11.40
100 Per Metre 11.40
125 Per Metre 11.40
150 Per Metre 11.40
180 Per Metre 13.10
200 Per Metre 14.80
225 Per Metre 15.60
250 Per Metre 16.70
300 Per Metre 21.40
350 Per Metre 38.70
380 Per Metre 40.80
400 Per Metre 42.00
450 Per Metre 47.60
500 Per Metre 51.30
530 Per Metre 58.40
560 Per Metre 64.00
600 Per Metre 68.30
650 Per Metre 70.70
680 Per Metre 75.00
700 Per Metre 83.10
750 Per Metre 96.00
800 Per Metre 111.20
900 Per Metre 133.40
1000 Per Metre 161.10
1100 Per Metre 191.50
1200 Per Metre 224.60
8. b. Lowering the C.I. Pipes, D.I. Pipes and fittings with flanged ends carefully into the trenches and laying them true to alignment and gradient including all sundries, but excluding conveyance from source of supply as per BIS No.3114/85.
DIAMETER OF PIPE : (D/F Pipes) in mm :
80 Per Metre 13.90
100 Per Metre 13.90
125 Per Metre 13.90
150 Per Metre 14.60
180 Per Metre 14.90
200 Per Metre 16.30
225 Per Metre 17.40
250 Per Metre 18.60
300 Per Metre 23.70
350 Per Metre 42.50
380 Per Metre 43.80
400 Per Metre 46.90
450 Per Metre 52.20
500 Per Metre 54.60
530 Per Metre 60.90
560 Per Metre 65.50
600 Per Metre 71.40
650 Per Metre 73.20
680 Per Metre 79.20
700 Per Metre 91.30
750 Per Metre 103.20
800 Per Metre 126.60
900 Per Metre 152.90
1000 Per Metre 181.10
1100 Per Metre 212.60
1200 Per Metre 247.70
9. a. Jointing the C.I. / DI Pipes & fittings with S/S ends excluding cost of jointing materials such as lead or lead wool and hemp yarn but including sundries such as cost of fuel for melting lead, filling with water, with a water lead upto 500 m and testing to required pressure complete. As per BIS No.3114/85.
DIAMETER OF PIPE : (S/S Pipes) in mm :
80 Each Joint 36.30
100 Each Joint 39.00
125 Each Joint 56.20
150 Each Joint 58.60
180 Each Joint 68.00
200 Each Joint 76.60
225 Each Joint 86.50
250 Each Joint 95.50
300 Each Joint 112.10
350 Each Joint 122.70
380 Each Joint 140.70
400 Each Joint 159.70
450 Each Joint 177.50
500 Each Joint 188.30
530 Each Joint 204.50
560 Each Joint 220.90
600 Each Joint 253.50
650 Each Joint 270.90
680 Each Joint 275.40
700 Each Joint 282.40
750 Each Joint 307.90
800 Each Joint 329.70
900 Each Joint 383.20
1000 Each Joint 434.50
1100 Each Joint 490.00
1200 Each Joint 539.30
9. b. Jointing the C.I. Pipes, D.I. Pipes & fittings with Rubber Gasket, excluding the cost of the gasket but including all sundries filling with water with a water lead upto 500 m and testing to required pressure etc., complete as per BIS No.3114/85.
DIAMETER OF PIPE :  in mm :
80 Each Joint 33.70
100 Each Joint 36.20
125 Each Joint 52.30
150 Each Joint 54.60
180 Each Joint 63.00
200 Each Joint 72.40
225 Each Joint 82.00
250 Each Joint 89.00
300 Each Joint 106.10
350 Each Joint 114.40
380 Each Joint 131.20
400 Each Joint 150.50
450 Each Joint 167.20
500 Each Joint 177.40
530 Each Joint 192.60
560 Each Joint 208.10
600 Each Joint 241.30
650 Each Joint 257.90
680 Each Joint 262.10
700 Each Joint 268.80
750 Each Joint 293.10
800 Each Joint 313.90
900 Each Joint 364.70
1000 Each Joint 413.60
1100 Each Joint 457.60
1200 Each Joint 500.90
10 Jointing the C.I. Pipes, fittings and valves with flanged ends excluding cost of jointing materials such as bolts, nuts, rubber insertion, white lead and including filling with water with a water lead upto 500 m and testing to required pressure etc., complete as per BIS No.3114/85.
DIAMETER OF PIPE :  in mm :
80 Each Joint 43.70
100 Each Joint 46.60
125 Each Joint 67.20
150 Each Joint 70.10
180 Each Joint 81.70
200 Each Joint 92.40
225 Each Joint 105.20
250 Each Joint 114.20
300 Each Joint 136.80
350 Each Joint 146.80
380 Each Joint 167.90
400 Each Joint 189.00
450 Each Joint 211.90
500 Each Joint 222.70
530 Each Joint 245.50
560 Each Joint 263.40
600 Each Joint 302.20
650 Each Joint 324.70
680 Each Joint 328.50
700 Each Joint 337.70
750 Each Joint 368.40
800 Each Joint 394.90
900 Each Joint 458.30
1000 Each Joint 550.40
1100 Each Joint 586.00
1200 Each Joint 646.00
11a Lowering the RCC pipes carefully into the trench laying them true to alignment and gradient, jointing RCC pipes with cement joints including curing, the cost of jointing materials i.e., Cement Mortar (1:1.5), hemp yarn etc., and testing including filling with water with a water lead upto 500 m as per BIS No.783/85.                                               per every 25 mm of  dia.  Per Metre 6.50
11b Lowering the RCC S/S pipes carefully into the trenches, laying them true to the alignment and gradient, jointing with rubber rings and testing including filling with water with a water lead upto 500 metres excluding cost of rubber rings as per BIS No.783/85. Per every 25 mm of dia. per meter. Per Metre 4.40
12 Laying, jointing of G.I.PVC/HDPE pipes and specials/fittings including excavation upto 0.5 m depth in all soils except rock requiring blasting and re-filling trenches after laying and jointing pipes.
a G.I. PIPES :
DIA in mm                                     
50 Per Metre 11.00
40 Per Metre 11.00
32 Per Metre 10.20
25 Per Metre 10.20
20 Per Metre 9.20
15 Per Metre 9.20
b PVC/HDPE pipes as per BIS No.7634 part-III/75 for PVC and BIS No.7634 part-II/75 for HDPE pipes.
DIA in mm                                     
50 Per Metre 10.20
40 Per Metre 10.20
32 Per Metre 9.30
25 Per Metre 9.30
20 Per Metre 8.50
NOTE :- (i) The above rates are applicable for the works in District only.
(ii) If the depth of excavation is more than 0.5 m separate rates to be worked out.
13 Lowering & laying AC pressure pipes in ready made trenches true to alignment and gradient including all sundries but excluding conveyance from source of supply, as per BIS No.6530/72.                       Dia of Pipes in mm.
80 Per Metre 6.50
100 Per Metre 6.50
125 Per Metre 6.50
150 Per Metre 6.80
200 Per Metre 8.30
250 Per Metre 9.50
300 Per Metre 11.60
350 Per Metre 20.40
400 Per Metre 22.90
450 Per Metre 25.50
500 Per Metre 30.40
600 Per Metre 32.50
14 Jointing AC pressure pipes with AC couplings or CID joints complete with Rubber Rings including filling with water with a water lead upto 500 m and testing to required pressure, etc., complete but excluding cost of jointing materials and conveyance of pipes from source of supply as per BIS No.6530/72.                                                       Dia of pipes in mm .
80 Each Joint 14.30
100 Each Joint 19.90
125 Each Joint 19.90
150 Each Joint 22.90
200 Each Joint 22.90
250 Each Joint 30.60
300 Each Joint 30.60
350 Each Joint 34.50
400 Each Joint 34.50
450 Each Joint 40.00
500 Each Joint 40.00
600 Each Joint 46.00
15 Lowering and laying in ready made trenches true to alignment and gradient, jointing and testing of stoneware pipes excluding cost of jointing materials such as cement mortar and hemp yarn as per BIS No. 4127/83.DIA of Pipes in mm .
100 Per Metre 17.30
150 Per Metre 21.80
200 Per Metre 24.30
225 Per Metre 25.40
250 Per Metre 29.00
300 Per Metre 33.30
400 Per Metre 37.10
450 Per Metre 49.90
16 Lowering, laying, jointing & testing to Hydraulic Field test pressure including cost of water with minimum water lead of 500 M (Labour charges only) for PVC pipes excluding the cost of jointing materials. outer Dia of Pipes in mm.
63 Per Metre 6.10
75 Per Metre 6.60
90 Per Metre 6.50
110 Per Metre 7.00
125 Per Metre 7.40
140 Per Metre 7.60
160 Per Metre 7.80
180 Per Metre 8.20
200 Per Metre 8.70
225 Per Metre 9.10
250 Per Metre 9.50
280 Per Metre 10.00
315 Per Metre 10.60
NOTE:- For item 9 to 16 the element of testing charges is to be considered as 20% of the combined rate for laying, jointing and testing. This 20% shall be released only after satisfactory testing of the pipe line to the required pressure.
17 Labour charges for lowering and keeping in position of C.I. Sluice valves, reflux valves and scour valves.  Dia of Valve in mm.
80 Each  17.10
100 Each  22.50
125 Each  29.50
150 Each  34.90
200 Each  64.70
250 Each  87.40
300 Each  132.50
350 Each  223.70
400 Each  274.40
450 Each  359.30
18 a. Labour charges for fixing Air Valves including boring the mains, threading the bore and fixing nipple etc., complete.  Dia of Air valve in mm.
25 Each  48.30
40 Each  55.30
50 Each  58.40
65 Each  62.30
80 Each  68.40
100 Each  80.30
125 Each  124.50
150 Each  136.10
18 b. Labour charges for fixing Kinetic Air Valves with isolating Sluice valves, Double Air valves/ Air Cushion valve excluding cost of jointing materials such as bolts, nuts and rubber insertions etc., complete. Dia of Air Valve in mm .
25 Each  48.00
40 Each  55.00
50 Each  58.10
65 Each  62.00
80 Each  68.10
100 Each  79.90
125 Each  123.90
150 Each  135.40
19 Labour charges for fixing fire hydrants excluding cost of jointing materials.
65 mm                                               Each  54.80
80 mm                                                Each  68.20
20 Uprooting C.I./ DI  Pipes by melting the lead, loosening the joints, scraping the pipes, hoisting and keeping within a lead of 10 m but excluding earth work excavation and refilling. Dia of Pipes in mm.
80 Per Metre 12.70
100 Per Metre 18.00
125 Per Metre 18.00
150 Per Metre 19.00
180 Per Metre 22.00
200 Per Metre 23.00
225 Per Metre 24.90
250 Per Metre 27.60
300 Per Metre 34.00
350 Per Metre 53.00
400 Per Metre 58.40
450 Per Metre 63.70
500 Per Metre 65.40
600 Per Metre 74.60
21 Uprooting of RCC pipes including breaking the collars, loosening the joint, scraping the pipes, hoisting and keeping within a lead of 10 m but excluding earthwork excavation and refilling.
Diameter of Pipes in mm               
100 Per Metre 6.60
150 Per Metre 6.70
225 Per Metre 9.00
300 Per Metre 9.90
22 Removing GI/PVC/HDPE pipes and specials/ fittings and clearing.
Dia of Pipes in mm    
50 50% of data of laying & jointing of GI/ PVC/ HDPE pipes and fittings of relevant PH item.
40 Per Metre
30 Per Metre
25 Per Metre
20 Per Metre
15 Per Metre
23 Cutting C.I./ DI Pipes without water in mains.Dia of pipes in mm.
80 Each cut 25.20
100 Each cut 25.20
125 Each cut 25.20
150 Each cut 25.20
180 Each cut 28.70
200 Each cut 28.70
225 Each cut 28.70
250 Each cut 41.40
300 Each cut 41.40
350 Each cut 57.60
380 Each cut 63.20
400 Each cut 65.90
450 Each cut 81.90
500 Each cut 98.50
530 Each cut 107.10
560 Each cut 115.60
600 Each cut 131.10
680 Each cut 147.90
24 Cutting A.C. Pipes without water in mains.Dia of pipes in mm.
80 Each cut 10.70
100 Each cut 10.70
125 Each cut 10.70
150 Each cut 10.70
200 Each cut 11.30
250 Each cut 18.30
300 Each cut 18.30
350 Each cut 22.90
400 Each cut 25.40
450 Each cut 31.10
500 Each cut 34.60
600 Each cut 38.70
25 Drilling and tapping CI/ DI Main and fixing brass screw down ferrule and plug.
10 mm to 20mm                         Each Tapping 52.60
25 mm to 40mm                          Each Tapping 62.80
26 Cutting road surface including stacking of excavated materials for pipe line trench work.
a) Cutting open B.T. road surface (as well as asphalt concrete upto 75 mm thick) including water bound macadam                                 10 Sqm 167.80
b) Cutting open C.C. road surface        1 Cum 310.20
c) Cutting open water bound macadam road including soiling                                    1 Cum 54.70
27 Bailing out water.(For PH item)
a) Bailing out water from the pipe line trenches with oil engine driven pumpsets, including hire charges, fuel charges and wages for Driver and Helper.                                                                                                   HP/Hour 11.00
b) Bailing out water from the pipe line trenches with Electric Driven pumpset including hire charges, current charges and wages for Driver and Helper.                                                                  HP/Hour 8.60
NOTE:- The rate is payable on the total H.P. hours ignoring fractions less than 0.5 HP hour and rounding off 0.5 HP hour or more to the next higher integer.
28 Shoring and strutting of trenches for water and sewer main.
a) Single Staging from (0 to 2.5 Mts.) 10 Sqm of Shoring area 498.00
b) Double staging from (2.5 m to 4.5 Mts.) 10 Sqm of Shoring area 673.30
29 Barricading, hoarding, lighting and watching etc., for water supply and sewerage works for trenches. 10 RM 26.90
30 Excavation of trenches for infiltration galleries, syphon lines and connecting mains in all soils under water including all leads, lifts, shoring, strutting, bailing out water and removal of shoring and strutting materials, after completion of pipe line work.
a) 0 to 1 m deep under water.             10 Cum 4051.00
b) 1 to 2 m deep under water.             10 Cum 5803.00
c) 2 to 5 m deep under water.        10 Cum 8376.00
d) Beyond 5 m deep under water for every additional 1 m depth over item 'c'                    10 Cum 1585.00
NOTE:- The above rates do not include rock requiring blasting or chiselling
31 Laying and jointing glazed stoneware pipes including loose jointing with cement fillets and all other incidental charges for infiltration gallery, inclusive of bailing out water by pumping to keep the trench reasonably dry to facilitate the work excluding cost of stoneware pipes.
a) 200 mm to 400 mm                        Per Metre 199.70
32 Laying and jointing perforated RCC pipes inclusive of bailing out water and jointing with cement fillets and all other incidental charges for infiltration gallery inclusive of bailing out water by pumping to keep the trench reasonably dry to facilitate the work excluding cost of perforated pipes and collars.
a) 200 mm to 600 mm                        Per Metre 206.10
33 Centring and scaffolding charges for RCC members including all materials and labour charges for forming and dismantling                                                      a) for R C C Elevated Service Reservoir of staging up to 15 metre below L W L.
1) Slabs for thickness (150 mm to 300 mm) One Sqm of Centering area 722.20
2) Slabs for thickness above (300 mm) 1443.80
3) Side walls curved surfaces. 545.90
4) Side wall straight surfaces. 485.50
5) Dome. 591.40
6) Roof Slab. 364.20
7) Column footing. 398.10
8) Column braces and beams 243.50
9) Circular braces, ring beams & circular column. 266.80
Note:- For RCC ELSR of staging above 15 m observed data may be worked out for the extra staging taking into consideration, the quantum of concrete to be lifted, extra scaffolding involved etc., and may be adopted in the working estimate after getting approval from the competent authority.
b) For Ground level works :-
1) Slabs                                     1 Sqm As per Common SSR
2) Beams & Lintels                   1 Sqm
3) Sun shades                            1 Sqm
4) RCC vertical walls of plane surface upto 3 m height such as ground level tanks clarifiers and sludge digesters etc.                                                  1 Sqm 268.80
5) RCC vertical walls of circular faces upto 3 m    height.                                                1 Sqm 337.20
NOTE: Scaffolding for every extra height of 1 m or part thereof but not less than 0.5 m - 10 Sqm. 10 Sqm
34 Lift or delift of materials :
a) Lifting of cement concrete for RCC elevated reservoir. For every 3 m height or part thereof over the initial lift of 5 m                             1 Cum 49.30
b) Delifting the materials such as stones, concrete etc., for concrete below ground level for construction of masonry ground level reservoirs, inspection wells, test wells and sump wells etc., for every 2 m depth or part thereof beyond the initial depth of 4 m from ground level             1 Cum 15.00
35 Labour charges for fixing ventilating shafts complete with all accessories.                               Each 203.50
36 Labour charges for fixing water closets including fixing of foot rests (for all sizes).  Each Relevant Common SSR item
37 Labour charges for fixing of flushing cistern including fixing of flush pipes, lead pipe, jointing etc., complete                                            Each
38 Labour charges for fixing wash hand basin including fixing of inlet and waste pipe connections etc., complete                                             Each
39 Fixing urinal with inlet and waste pipe connections etc., complete.                                     Each
40 Refilling the trench for pipe line with excavated earth including watering and tamping etc., complete                                          10 Cum
41 a Extra allowance for isolated scattered works viz., valve pits, public fountains, meter pits and manholes etc., complete.                                        Each 25% extra over the cost of chamber.
41 b  Repairs to the existing mains, interconnections, replacement of valves/specials etc., including the cutting ,jointing, bailing out of water, drying, earth work execavation etc., complete. 100% extra over the cost of work
42 Removal of wet silt and sludge from sullage drains with aid of baskets and vessels.         10 Cum 479.70
43 Conveyance of C.I./ DI  Pipes, C.I. Special excluding loading, unloading and stacking. As per separate sheet enclosed
44 Conveyance of RCC pipes including loading, unloading and stacking. Deleted
45 Conveyance of Stoneware pipes inlcuding loading unloading and stacking. As per local competitive quotations
46 Conveyance of A.C. pressure pipes and accessories including loading, unloading and stacking. As per local competitive quotations
47 Conveyance of PVC pipes and accessories including loading, unloading and stacking. Deleted
48 Well sinking in sandy and other loose soils under water either by manual labour, divers, or dredgers, weighting the top of staining to assist sinking etc., including dewatering and other incidental charges such as hire charges for mechanical equipment etc., complete upto 4 m internal dia.
Upto 2 m below GL/m                    Per metre 8060.00
From 2 to 4 m below GL/m                  Per metre 8827.00
From 4 to 6 m below GL/m                  Per metre 9978.00
From 6 to 8 m below GL/m                   Per metre 11251.00
From 8 to 10 m below GL/m                Per metre 12437.00
Note:-Below 10 m for every metre depth or part thereof add Rs.250/- per m. For higher dia, observed data is to be prepared and got approved.
49 Sinking in Hard strata other than rock but in soils like limestone, gravel, clay under water including, pumping dewatering, hire charges for mechanical equipment etc., complete. Deleted
50 Open well excavation in various soils. As per Common SSR
51 Rates for OHSRs/ELSRs including fixtures with a staging of 15 m.
a  Capacity in  500 Kilo litres Per litre 3.90
b  Capacity in 1000 Kilo litres Per litre 3.70
c  Capacity in 1500 Kilo litres Per litre 3.60
d  Capacity in 2000 Kilo litres Per litre 3.40
e  Capacity in 2500 Kilo litres Per litre 3.20
 NOTE : -1) The above rates are applicable for reservoirs with independent footings and rate of Rs.3,000/- per tonne for cement and Rs.15,000/- per tonne for steel.
2) For every m height of staging above 15 m or less than 15 m the rate shall be increased/reduced by Rs.0.02 paise per litre.
3) For every Rs.100/- increase/decrease in price of cement per tonne increase/decrease the rate by 0.7%
4) for every Rs.1000/- increase/decrease in price of steel per tonne, increase/decrease the rate by 2%
5) Rate inclusion of three coats of epoxy paint to inner surface of the reservoir including roof dome.
6) For intermediate ranges proportional rates may be adopted.
7) The above rates be adopted for estimate purposes for construction of ELSR for a finished work including 2 coats of snowcem painting for external surfaces, lettering  fixing of all required fixtures, pipes, bends, valves etc., for pipe connections but excluding cost of pipes, bends and valves as per Departmental designs and drawings.
8) The above rates are arrived considering a wind pressure  as per BIS No.875/88 
9) For tribal/Agency area, the above rates shall be increased by 5%
10) Fixtures include.
a) A balcony of 0.75 m width at floor slab level/ middle ring beam level with RCC/GI pipe hand railing.
b) C.I. Manhole frame and cover : 0.60 x 0.6 m size  2 Nos.
c) RCC Mosquito proof ventilators.
d) RCC Finial - 1 No.
e) RCC precast ladders 0.45 m wide - 2 Nos.
f) RCC dog legged stair case of 1.00 m  width with hand railing - 1 No.
g) RCC hand railing 0.75 m height alround at top of reservoir.
h) Water level indicator of approved pattern - 1 No.
i) Lightening arrestor with all its accessories complete including earthing - 1 No.
52 Rates for OHSRs/ELSRs including fixtures with a staging of 15 m.
a  40,000   Litres capacity                                Per litre 9.30
b  40,001   to  60,000 Litres capacity                                Per litre 7.00
c  60,001   to 1,00,000 Litres capacity                                Per litre 6.50
d  1,00,001   to 2,00,000 Litres capacity                                Per litre 5.70
e  2,00,001   to 3,00,000 Litres capacity                                Per litre 5.30
f  3,00,001   to  4,00,000 Litres capacity                                Per litre 4.70
g 4,00,001   to  4,50,000 Litres capacity                                Per litre 4.10
 NOTE: -1) The above rates are applicable for elevated level services reservoirs (OHSRs) with independent footings and a rate of Rs.3,000/- per tonne for cement and Rs.15,000/- per tonne for steel.
2) For every metre height of staging above 15 m or less than 15 m, the rate shall be increase/reduced by Rs.0.02 paise per litre.
3) For every Rs.100/- increase/decrease in price of cement per tonne increase/decrease the rate by 0.7%
4) For every Rs.1000/- increase/decrease in price of steel per tonne increase/decrease the rate by 2%
5) Rate inclusive of  three coats of epoxy paint to inner surface of the reservoir including roof dome.
6) For intermediate ranges proportional rates may be adopted.
7) The above rates be adopted for estimate purposes for construction of ELSR for a finished work including 2 coats of snowcem painting for external surfaces, lettering, fixing of all required fixtures, pipes, bends, valves etc., for pipe connections, but excluding cost of pipes, bends and valves, as per departmental designs and drawings.
8) The above rates are arrived considering a wind pressure as per  BIS No.875/88 
9) For Tribal/Agency area, the above rates shall be increased by 5%.
10) Fixtures include :
a) RCC or Aluminium ladder inside 0.45 m wide.
b) Dog legged staircase of 1.0 m wide.
c) M.S. Ladder/spiral on the outside.
d) Lightening arrestor, including conductor and earthing etc.
e) RCC ventilators with copper or stainless steel fly proof mesh.
f) RCC finial ventilators with copper or stainless steel fly proof mesh.
g) Manholes frame and cover 0.75x0.75 m with frame as per IS specifications (light duty) - 2 Nos.
h) Railing with 32 mm dia G.I. Pipes (A class) in two rows around OHSR fixed in RCC (1:2:4) posts of size 100x75x75 mm with 1.5 m intervals around periphery on top of the OHSR for smaller capacities.
i) Water level indicator of good quality with ebonite/ copper float approved pattern- 1 No.
53 Construction of rapid gravity filtration plant including civil, mechanical and electrical trial running etc., complete.
1)  0 - 2.0 Mld capacity                 Per litre 1.50
2)  Above 2.0 & upto 5.0 Mld               Per litre 1.30
3)  Above 5.0 & upto 10.0 Mld              Per litre 1.20
4)  Above 10.0 & upto 20.0 Mld            Per litre 1.10
5)  Above 20.0 Mld                               Per litre 0.90
NOTE: - a) The above rates are applicable with cement @ rate of Rs.3,000/-MT and steel of 15,000/MT.
b) For every Rs.100/MT increase/decrease the price of cement increase/reduce the rate by 0.7%.
c) For every Rs.1000/MT increase/decrease in price of steel increase/reduce the rate by 2%.
NOTE:-The cement rate is to be checked with District Collector and R & B Dept. regularly and correction carried in respect of rates where use of cement is involved.